Project code: 1702231
Location
Barcelona, TMB Triangle Ferroviari Depots.
Date
June 2017 – September 2018
Useful information
CT power 3200 kVA.
Installed power 1100 kW
Charger power 50 kW
Description
Installation of charging infrastructure for 22 charging units, each with a capacity of 50 kW. A 25 kV MV line has been laid from the Metering Centre to a new Transformer Centre in the bus depot. This centre is equipped with two 1,600 kVA transformers and the corresponding MV, LV and Coms rooms. The civil works for the installation of the chargers, sub-panels and bells have been carried out.
We use cookies to ensure that we provide you with the best possible experience on our website. If you continue to use this site, we will assume that you agree to this.