Project drafting and technical specifications services for the Bus Electric Recharging Station (EREA) Line H16 Zona Franca Forum
Home » Project drafting and technical specifications services for the Bus Electric Recharging Station (EREA) Line H16 Zona Franca Forum
Project code: 1603126
Location
Barcelona, Eduard Maristany Avenue.
Date
July 2016 – July 2018
Useful information
CT power 1000 kVA.
Cable length in tunnel 3 km
Charger power 500 kW
Cable length on street 350 m
Description
Installation of 500 kW charging infrastructure for electric buses on the H-16 line. The project required the laying of 3 km of 25 kV MV cable inside the underground tunnel from the TMB substation to a new transformer station at the charging point location. An enclosure below street level was constructed using micropiles, where the transformer station was installed. The rectifier is powered from the transformer station. The new charging infrastructure and other complementary systems (PCI, etc.) have also been integrated into the TMB infrastructure.
We use cookies to ensure that we provide you with the best possible experience on our website. If you continue to use this site, we will assume that you agree to this.