FRAMEWORK AGREEMENT FOR ENGINEERING SERVICES FOR ZUNDER CHARGING STATIONS IN SPAIN
Home » FRAMEWORK AGREEMENT FOR ENGINEERING SERVICES FOR ZUNDER CHARGING STATIONS IN SPAIN
Project code: 00000
Location
Spain
Date
August 2018 – January 2021
Useful information
Contracted power 100–200 kW
Installed power 150 kW
Charger power 44–50 kW
Low voltage supply
Description
ZUNDER built a network of 100 fast and ultra-fast charging stations at service stations and establishments adjacent to Spain’s main roads. Eight charging facilities have been installed, totalling 1,200 kW. Evectra’s tasks included drafting the construction engineering project, processing building licences and permits, project management, health and safety coordination, and legalisation of the low-voltage installation.